We're Expanding ... Again!

amerilux building expansion 2017Since being formed in May 2004, AmeriLux International has expanded its current facility twice. In 2009, we expanded the distribution center and operations space, nearly doubling the physical plant size. In 2012, we completed another expansion to the distribution center; bringing the total square footage of operations space to just under 60,000 square feet.

This time, AmeriLux is adding an additional building. The 30,592 square foot facility is being built on the vacant property adjacent to our East De Pere location and will house our extensive inventory of multiwall polycarbonate products. The new building will have 161 unique storage locations; providing us the opportunity to improve our lot control, minimize double handling of material, and allow for a true FIFO inventory system.

Progress photos and updates will be added regularly, so check back often!


Building Expansion Update: September 22nd, 2017
On Monday, AmeriLux International held its 2nd Annual Family Picnic. Neighboring businesses and key partners were invited to this family-friendly event that included a bounce house, arcade games, henna, and music. Food and beverages were provided by the Salvation Army, giving us an opportunity to give back while celebrating.

The festivities kicked off with a special flag raising ceremony, celebrating the completion of our new building. Kurt Voss, AmeriLux CEO, delivered heartfelt words to the group before he and several others raised a large American flag. The flag measures 20 feet by 30 feet and makes quite an impressive statement on the AmeriLux campus. “Is this a great country, or what…?!”

A very big THANK YOU to everyone involved in the construction of our new building and to all who came out to celebrate with us!

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: September 8th, 2017
The crew continued their work this week transforming and expanding the existing landscape. There was a lot of excitement mid-week when an 80-foot-tall flagpole was erected in front of our main building. With the help of a crane, the pole was hoisted into a metal sleeve within a 6-foot-wide, 8-foot-deep, concrete-filled hole. The pole was centered, plumbed vertically, and set with 800-pounds of sand. There will be a special flag raising ceremony on Monday, September 18th.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017


Building Expansion Update: September 1st, 2017
Construction of our new building is nearly complete. Besides a few minor issues that are being addressed, everything’s coming together nicely. On the inside, the phone and paging system is now operational as well as the wireless network; providing a means of effective communication and coordination between our two facilities. Outside, the retention ponds are built and the final grading is complete. Landscaping began this Monday and will continue for several weeks.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017


Building Expansion Update: August 25th, 2017
The excavation crew built a retention pond in the front of the new building this week as well as finished the final grading. The Multidirectional Sideloader was busy moving material and filling the new racking system with long pallets of polycarbonate panels. The vertical nature of the racking system makes excellent use of floor space, offers optimal storage, and allows for easy access to inventory.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: August 17th, 2017
The final coat of asphalt was laid on the new parking lot yesterday, giving it a smooth finish. The lot striping was painted on and additional ADA-compliant spaces were created. These new accessible parking stalls along with an existing one feature a redesigned accessible icon. The new design displays an active, engaged image with the focus on the person, not just the disability.

The Accessible Icon Project started as a graffiti movement in Massachusetts, and has now grown internationally. The movement is focused on changing the perceptions towards disability. Learn more about this project at www.accessibleicon.org or http://www.nolimitsgb.org/accessible-icon.html

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: August 16th, 2017
The new material handler has been assembled and completed its first ‘test run’ this week. Other than a few minor hiccups, several pallets of multiwall polycarbonate panels were successfully moved and lifted into the racking system. Overall, everything went smoothly and the Multidirectional Sideloader performed as expected.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: August 11th, 2017
The asphalt crew finalized the area adjacent to the new building earlier this week. Because of the heavy rain last week, the crew will need to return at a later date to put the final coat on the new parking lot. The installation of the racking is complete. Movement of the multiwall polycarbonate product line to the new building will begin next week.

Yesterday, the new Multidirectional Sideloader was delivered. Designed to move long pallets of product, this custom-built material handler will significantly reduce the amount of time spent moving polycarbonate panels in and out of the rack system. AmeriLux has invested heavily in racking and material handling equipment to improve efficiencies, quality, safety, and inventory control.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: August 4th, 2017
Multiple crews were busy inside the new building this week. Electrical and plumbing work continued. The fire pump has been installed. Maximizing space, a compressor now sits on top of the fire pump room.  The three interior rooms have been drywalled and trim work painted.

Installation of racking began this week. The new building will have 161 unique storage locations. This will improve lot control, minimize double handling of material, and allow for a true FIFO inventory system. Outside, the new parking lot has been paved with asphalt along with an area in the shipping and receiving yard.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: July 28th, 2017
The exterior of the building is looking great. All the doors, including the overhead doors, have been installed. Final grading around the new building is underway. Excavation work continued on the retention ponds. Interior work included: Running compressed air lines and installation of the fire pump.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: July 21st, 2017
Work continued this week on the interior – power hook up, sprinkler system installation, and the hanging of sheetrock. Exterior work included: pouring the loading dock area, building concrete steps, and extending the existing sidewalk in front of our current facility. The excavation crew was also back, making some more progress on the drainage system.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: July 12th, 2017
All the concrete has been poured and the floor is complete. This week, the fire sprinkler system and ceiling light fixtures are being installed. Three small interior rooms are also taking shape – the fire pump room, a restroom, and an office space.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: June 22nd, 2017
After a brief lull last week, the construction crew is back at it and making progress on the concrete floor. The first loads of concrete have been delivered and poured. Two riding trowel machines have been busy spinning around, smoothing the concrete.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: June 9th, 2017
Installation of the blue THERMOCLICK™ panels is complete on three sides of the building. Gutters and downspouts are being installed. The roof is finished and work on the inside has begun. Underground conduit has been laid. The interior of the building’s steel frame – walls, beams, and columns – have been painted a brilliant white, allowing for natural light reflection.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 31st, 2017
The sides and ends of the steel framework are now covered with metal siding. Installation of the THERMOCLICK™ panels is complete on the side walls. The roofing is well underway and should be complete this week.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 23rd, 2017
The exterior brick masonry work is complete and complements our existing building nicely. Roofing installation has begun on the north half of the roof. Siding will continue to be installed this week.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 19th, 2017
The construction crew is making great progress on the new building even with the rain delays. Siding is now being installed on the side walls. The new building is really taking shape!

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 15th, 2017
Incorporating natural light into the design of our new building was very important. All four sides of the building will feature our 40mm Blue LEXAN™ THERMOCLICK™ interlocking sheet system. Click here to learn more about this daylighting product.

amerilux building expansion 2017amerilux building expansion2017amerilux building expansion 2017

 

Building Expansion Update: May 11th, 2017
Siding has begun. The back end of the building is nearly complete. The front of the building will feature a partial-height masonry wall. The brick design will match our existing building.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 10th, 2017
The structural steel frame for our new building is complete. Frame openings for the doors are finished.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 3rd, 2017
The steel skeleton of the new building is taking shape. Roof construction is underway. Huge steel trusses are being hoisted into place by a crane.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: May 2nd, 2017
The steel is going up. The new building is going to be double the height of our current facility. Wow – so this is what 40 feet high looks like!

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: April 27th, 2017

The steel has arrived! Over the next couple of weeks, the construction crew will assemble and erect the building’s steel frame. It’s going to be exciting to watch the new building materialize!

amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: April 18th, 2017

Backfill process is complete. Steel for the new building is scheduled to be delivered next week. Site work continues on the storm water and foundation drainage system.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: April 13th, 2017

The expansion to the front parking lot is taking shape. Crews have been busy this week spreading gravel and packing it down. Soon we will have plenty of parking for employees and visitors.

amerilux building expansion 2017amerilux buidling expansion 2017amerilux building expansion 2017

 

Building Expansion Update: April 5th, 2017

Foundation walls are complete. The excavation crew is working hard. Backfilling is underway.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: March 29th, 2017

Things are starting to take shape as work continues on the foundation wall.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: March 23rd, 2017

Concrete reinforcing wall form work is underway and footing work continues. Some footings have been poured. The excavation crew continues to make progress on the parking lot expansion.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: March 20th, 2017

Dirt is on the move! The crew continues to excavate soil in the area that will be the expanded parking lot. Work on footings for the new building is underway.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update: March 17th, 2017

The excavation crew has been busy moving a lot of dirt, preparing the site for the expansion of the front parking lot.

amerilux building expansion 2017amerilux buildign expansionamerilux building expansion 2017

 

Building Expansion Update: March 15th, 2017

Site work continues in preparation for the initial footing excavation.

amerilux building expansion 2017amerilux building expansion 2017amerilux building expansion 2017

 

Building Expansion Update:March 10th, 2017

Site preparation has begun! Heavy equipment moved in and the excavation crew began clearing the site of vegetation, brushwood, and other debris.

amerilux building expansion 2017amerilux building expansion 2017

 

 